LeJeune Steel Company
Consultant
and Technical Expert to LeJeune Steel Company and its
attorneys on various change orders, requests for equitable
adjustment, and successful dispute resolution in state
court. LeJeune Steel was responsible for a multi-million
dollar contract to furnish, fabricate, and erect complex
structural steel components for the Millennium Park Outdoor
Music Pavilion Project in downtown Chicago, Illinois.
Duggan and Rhodes Group, LLC (DRG)
Consultant
and Technical Expert to DRG and its attorney client
representing Indiana University of Pennsylvania (IUP).
IUP’s contractor, Cooper Industries, was responsible for
design and installation of a 24MW co-generation facility
using reciprocating engines and waste heat recovery to
provide electrical energy, steam, and hot water heat to IUP.
Provided services for measuring incurred damages and
supporting dispute settlement arising out of breach of
contract and other actions by Cooper Industries that
adversely affected energy production for IUP use.
Consultant and Technical Expert to DRG
and its attorney client representing Lurges Lentjes North
America, Inc (LLNA). LLNA was responsible for the
engineering, procurement and construction of two selective
catalytic reduction units for Units 1 and 2 at the PSEG
Mercer Station located in New Jersey. Evaluated the project
percent complete, measured the values of completed and
uncompleted work at the time of an unexpected contract
termination for default by LLNA’s utility client, and
reviewed utility counterclaims. Provided technical expert
services and provided testimony before an arbitration panel
regarding these matters. |
|
Fluor Fernald
Consultant
and Technical Expert to Fluor Fernald and its attorneys in a
dispute over settlement costs arising from its termination
of a subcontractor for convenience. The subcontract was for
a multi-million dollar complex environmental nuclear cleanup
project at the Department of Energy, Fernald Site located in
Ohio. In anticipation of litigation, provided cost
engineering services and other services for the detailed
analysis of estimates of project craft labor productivity
and other costs to derive certain reasonable cost impacts.
British Nuclear Fuels Limited, Inc (BNFL)
Consultant and Technical Expert to BNFL, Inc. on various
change order and request for adjustment matters related to a
several hundred million dollar prime contract with the
Department of Energy. BNFL was under contract for the
decontamination, decommissioning, and recycling services for
three Gaseous Diffusion Plant buildings (K-29, K-31, and
K-33) in the East Tennessee Technology Park (formerly the
K-25 Site) in Oakridge, TN. Responsible for providing
strategic guidance, thought leadership, and technical
support services in support of efforts to successfully
recover costs associated with the impacts arising from many
unforeseeable direct impact changes that occurred during the
contract lifecycle. Services included 1.) Preparation of
“as-planned” project schedules and other initial project
performance baselines; 2.) Forensic (retrospective)
reconstruction and support of the “as-built” project
schedule and other actual performance indicators; and 3.)
Schedule and other performance variance analysis from
“as-planned”. This work was used to i.) Identify and
segregate the changes attributable to the government and/or
any other causal factors, ii.) Measure the schedule and
performance impact of the changes and quantify the resultant
costs, and iii.) Support the measurement and pricing of
claims for delay, disruption, interference, acceleration,
and any other impacts. |